Pindula
Register Login

ZESA Increases Load Shedding After Shutting Down 3 Units At Kariba

ZESA Increases Load Shedding After Shutting Down 3 Units At Kariba

The country’s power utility, ZESA Holdings, has announced increased load shedding due to depressed power generation at the Kariba power station.

In a public notice, ZESA said it is carrying out refurbishment works on the Kariba Dam wall, therefore, necessitating the shutting down of three power generation units at the power station. The notice read:

ZESA Holdings would like to advise its valued customers countrywide that there is an increase in load shedding outside the publicised schedules due to the refurbishment works on the Kariba Dam wall.

The refurbishment works have resulted in the taking out of 3 units at Kariba South Hydro Power Station today, 14th December 2021.

The power utility further advises that this has resulted in a depressed generation, resulting in an increase in load shedding.

Consumers are advised to use the available power sparingly to minimize the effects of load shedding.

The inconvenience caused is sincerely regretted.

More: Pindula News

Share Article

Sponsored

More

9 Comments

Muchakaka🤣 Kakistocracy 6 months ago

Haaaaa dai 2023 wacho angosvika next year zvigare zvaitwa zvapera. Izvi hazviiti izvi. Vana KundaKinde NjugaDzarema ava vatinetsa. Apa havabvumi kuti zvarema.


Imwe mbeu 6 months ago

Thanks for letting us know @Pindula. But the difference is the same whether there's loadshedding or not...🤭


jah 6 months ago

imwe ere load shedding futi, isu tagara tiri load shedding nechekare ere mukurevei ?


WILLIAM SONBOY CHINEMBIRI 6 months ago

IF THERE IS ANY SECTOR THIS GOVERNMENT HAS FAILED IS THE ELECTRICITY SECTOR. TODAY IT IS THIS AND TOMORROW IT IS THAT. TODAY THEY TELL US THAT THEY ARE GOING TO IMPORT ELECTRICITY FROM KAFUE IN ZAMBIA. TOMORROW THEY WILL TELL US THAT THEY ARE GOING TO IMPORT ELECTRICITY FROM KABHORABHASA IN MOZAMBIQUE. WHICH IS WHICH ?

IF THESE GUYS ARE UNABLE TO RUN THIS COUNTRY PROPERLY, THEY SHOULD LET OTHERS FILL THE GAP. THERE ARE OTHERS WHO ARE WAITING IN THE WINGS READY TO RULE THE REPUBLIC OF ZIMBABWE.

WE ARE EXPERIENCING 9 HOUR LOAD SHADING STINTS. WE NO LONGER WANT THESE GUYS TO TELL US WHAT THEY ARE GOING TO DO TODAY AND TOMORROW, NO [NADA]. WE ARE TIRED OF FAKE PROMISES. WE NOW WANT TO SEE PROGRESS ON THE GROUND.

PROPOPULO, PROPATRIA, PROLEGE.

YOURS SINCERELY
CDE KUFA KWANGU ZVAROVA
[THE BUSH LAWYER]


Cde. ED Mangwana 6 months ago

2023 Pakaipa!


ELIÉF 6 months ago

Ngaapinde hake mkomana


Constable Tsuro 6 months ago

2023 Nyika iri kuzonaka


Sponsored

More
sadney 6 months ago

Refurbishment without improvement is just a mere hot air.How did the Chinese mega expansion drive end? We are sick and tired of these lies...


Chapwititi 6 months ago

Musanyepe,ingotii kune Load Shedding,kwete kutiudza nhorowondo and Load shedding yacho yakatanga at least 2weeks ago,ndopomonyepa kuti tavhara magwenya nhasi.Regai hake apinde mukoma



Leave a comment


Recent News


News Categories



Give us Feedback