Technical Faults Hit Kariba, Hwange Power Plants - ZESA

Technical Faults Hit Kariba, Hwange Power Plants - ZESA

The Zimbabwe Electricity Transmission and Distribution Company (ZETDC) on Sunday said it was experiencing depressed electricity generation due to technical faults at Kariba Hydroelectric Power Plant and Hwange Thermal Power Plant.

Since early last week, most parts of the country have been experiencing longer power outages, with some areas going for 16 hours without electricity.

In a public notice, ZETDC urged electricity users to protect their electrical gadgets by switching them off during power outages. Reads the notice:

Zimbabwe Electricity Transmission and Distribution Company (ZETDC) would like to advise its valued customers that it is experiencing depressed electricity generation and as a result, there is increased pressure on the grid. This is due to technical faults at Hwange and Kariba power stations.

Customers are therefore advised to use electricity sparingly and to switch off all electrical appliances during the outages to minimise the risk of possible damage to these appliances.

All stakeholders are assured that our teams are working round the clock to ensure restoration of service.

Share Article

Sponsored

10 Comments

choko 2 months ago

vakuru vekufinhura


Int 2 months ago

Zvakasiwa neVarungu veRhodesia Zvaora izvi pakuda. Zvinyowani


Kanda 2 months ago

Togara tichizvitaura pano don't rely on Smith regime power infrastructure

Asalif 2 months ago

The new one is also faulty nhai?? hakuna kwatinosvika nenhema dzenyu more over you are telling us about the fault today after the nation spent the weekend in darkness


Vesto 2 months ago

Hurumende yeZANU, zvemagetsi zvaramba. Chiregai kutambisa mari muchipa ZESA. Mari iyoyo chitengai makenduru mopa vanhu :-
Presidential Candles zvipere


milliyan 2 months ago

😂😂😂@Vesto boe ere

2 months ago

Citizens hardly go for a month without hearing ZESA reporting a fault at either Kariba Hydroelectric Power Plant or Hwange Thermal Power Plant.

This is a sign of long age or poor workmanship in maintenance. The infrastructure which was taken over from the Rhodesia Front Government is now old and needs replacement.

[ CITIZENS USED TO REFER TO ZESA AS MOTO MUZHINJI, BUT NOW IT IS REFERRED TO AS ZESA MOTO MUSHOMA ].

[PAMA HARMONISED ELECTIONS APA MUNA 2023 VERUZHINJI NGAVARASE ZANU PF VAVHOTERE CCC POLITICAL PARTY KUTI PAVE NE GUTSARUZHINJI NE HUTONGI HWEJEKERERE ].

Yours sincerely
William Sonboy CHINEMBIRI
[THE BUSH LAWYER4CCC].


Sponsored

2 months ago

the older you become the useless you will be
this should be the lesson to Zimbabweans who still want to vote Mnangagwa in.
it will fault after fault as he gets older


Vesto 2 months ago

Taura hako iwe.
Kuswerozvuzvurudzana netudhara tune tuche.nde twasweroputana tusisina kana muto.

Glen view resident 2 months ago

ZACC please check on electricity distribution in Glen view , there is an element of corruption there. Pane area yanetsa nekushaiswa magetsi whilest the other part rinoenda makomva area and Glen view 8 rinenge risina magetsi, vanhu vemashops they might be contributing to that because side iroro magetsi anoswera ariko haaendi.please ZACC taneta